1
Before
Site survey: roof, shading, panel, service size
2
Design and plan set
Single-line, site plan, structural/attachment details. Some cities require a stamped structural letter.
3
Permit
Utility interconnection application
Submit before or alongside the permit; approval to install is often required first.
4
Pull the building + electrical permit (or combined solar permit)
Check for a SolarAPP+ or express path.
5
Before
HOA approval if applicable
6
Work
Install racking, modules, inverter, disconnects, labeling
7
Inspection
City inspection (rough / final)
8
Closeout
Utility permission to operate (PTO)
Submit the passed inspection; meter swap if needed.
9
Commission and hand off monitoring

Looking for a specific city? Find the permits that apply.